Hi All,
We are facing issue on STD report(Report Painter) on PS module .
Report name : S_ALR_87013558 [Budget/Actual/Commitmt/Rem.Plan/Assg ]
Issue : Commitment values are not getting updated when i delete the PO line items .
Ex :
For WBS " M-455-01-01-05 " i am creating PO with 2 lines ( each 100$ ).
Once created the PO i can see the 200$ in report - commitment column. but if delete the one of my row in PO (ex : line 1 ) , then my report should show only 100$. but my report is showing 200$.
I have gone through the following SAPnote : 1746429 - How to correct commitment inconsistencies.but this one also not help full.
SAPnote : 1746429 Resolution
1. Please run report RKANBU01 for the incorrect projects in question, this will update any incorrect commitments. Further details can be found in note 152571.
2. After running the reports above, please run report RKACOR04 as this will correct any problems between the line item tables and the total record tables.
3. After running the above reports, please run transaction code CJEN for all the projects as this is very important so that the database gets updated.
4. Finally run report CJBN which rebuilds the availability control for each project.
If anybody help me out for this case .?